February 3, 2017

Current Projects

Core Campus Project Renderings – Robinson Hall/Harris theater


Fairfax Campus

Improve Utility Distribution Infrastructure Fairfax (August 2018 - November 2021)

 

Details

Project Number: 18208-000
Project Type: Construction
Campus: Fairfax
Biennium: 2016 -2018
Authorization: Authorized
Phase: Preliminary Design
Key Building Occupants:

Budget

Current Budget Total: 51,307,000

Schedule

Project Authorization:
Design Start: April 2016
Design Complete: August 2018
Construction Start: August 2018
Construction Completion: November 2021
Furniture Installation Completion:
Occupancy (ready for use):

Mason Executive Committee

Anne Holton, Interim University President
Frank Neville, Chief of Staff, Vice President, Communications and Marketing
S David Wu, Provost and Executive Vice President
Carol D. Kissal, Senior Vice President, Administration and Finance
Sean Mallon, Associate Vice President, Entrepreneurship and Innovation
Ann Ardis, Dean, College of Humanities and Social Sciences
Frank Strike, Vice President, Facilities

Mason Staffing

Cathy Wolfe-Pinskey, Program Director, Facilities
Lisa Reeves, Project Administrator
Michelle Gettle, Project Manager
Greg Rahimzadeh, Inspector
Mirwais Safi, Inspector
Fernando Acosta, Student Intern

Architect Team

Paul Harney, Architect, Principal, Perkins+Will
Sherman Lai, Project Architect, Perkins+Will
Stephanie Wolfgang, Landscape Architect, Perkins+Will
Justin Cooper, Senior Landscape Architect, Perkins+Will

Construction Manager Team

K.C. Haile, Senior Vice President, The Whiting-Turner Contracting Company
Jeff Downs, Project Manager, The Whiting-Turner Contracting Company
Perry Mahle, Project Manager, The Whiting-Turner Contracting Company
Rob Driscoll, Senior Superintendent, The Whiting-Turner Contracting Company

 

Construct/Renovate Robinson Hall and Harris Theater (September 2018 - January 2022)

PROJECT MAP                  PROJECT TIMELINE

Details

Project Number: 18207-000
Project Type: New Construction
Campus: Fairfax
Biennium: 2016 -2018
Authorization: Authorized
Phase: Design
Key Building Occupants: CHSS, MIX, University Classrooms, ITU
Project Webcam

Budget

Construction Budget: 108,316,000

Schedule

Project Authorization
Design Start: April 2016
Design Complete: November 2018
Construction Start: September 2018
Construction Completion: January 2022
Furniture Installation Completion: December 2021
Occupancy (ready for use): January 2021 – New Robinson, January 2022 – Renovated Harris

Mason Executive Committee

Anne Holton, Interim University President
Frank Neville, Chief of Staff, Vice President, Communications and Marketing
S David Wu, Provost and Executive Vice President
Carol D. Kissal, Senior Vice President, Administration and Finance
Sean Mallon, Associate Vice President, Entrepreneurship and Innovation
Ann Ardis, Dean, College of Humanities and Social Sciences
Frank Strike, Vice President, Facilities

Mason Staffing

Cathy Wolfe-Pinskey, Program Director, Facilities
Lisa Reeves, Project Administrator
Michelle Gettle, Project Manager
Greg Rahimzadeh, Inspector
Mirwais Safi, Inspector
Fernando Acosta, Student Intern

Architect Team

Paul Harney, Architect, Principal, Perkins+Will
Sherman Lai, Project Architect, Perkins+Will
Stephanie Wolfgang, Landscape Architect, Perkins+Will
Justin Cooper, Senior Landscape Architect, Perkins+Will

Construction Manager Team

K.C. Haile, Senior Vice President, The Whiting-Turner Contracting Company
Jeff Downs, Project Manager, The Whiting-Turner Contracting Company
Perry Mahle, Project Manager, The Whiting-Turner Contracting Company
Rob Driscoll, Senior Superintendent, The Whiting-Turner Contracting Company


Science and Technology Campus

Bull Run Hall Addition, Academic VIII (May 2019 - June 2023)


BULL RUN HALL 2, ACADEMIC VIII,
and DISCOVERY PROGRAMMING KICKOFF
May 2019 – June 2023

Project Goals:

George Mason University intends to develop a building program for a new 200,000 GSF instructional building, Academic VIII. The program is to be developed concurrently and coordianted with the program development for the Bull Run Hall Addition. The intention of the joint programming effort is to identify programmatic needs at the Sci Tech Campus to holistically plan for the growth and development of that campus in support of Mason’s initiatve to transform the Sci Tech Campus into a fully functional campus to serve STEAM-H students and provide those students with the full array of academic offerings and university life experiences associated with a tradtional campus experience.

Description of Project:

This project supports the continuing expansion of STEM-H programs at Mason, and is the first of several buildings to be programmed in a new STEM-H complex on our SciTech campus in Manassas, VA. A 200,000 GSF building, Academic VIII will support students enrolled in STEM-H majors, such as but not limited to kinesiology, materials science, forensic science, bioengineering, and mechanical engineering. Academic VIII will also support post-baccalaureate and related graduate-level medical/health programs for students pursuing careers in the healthcare and wellness professions. The building will include specialized instructional labs, classrooms, experiential learning collaboratories, and faculty and administrator offices to support growing student and faculty communities on SciTech campus. With the addition of Academic VIII, and the co-development of the Innovation Town Center immediately adjacent to and contiguous with its SciTech campus, Mason will provide a residential campus experience for students enrolling in relevant STEM-H programs from freshman year through PhD. Mason’s increasingly vibrant SciTech campus will serve as a magnet to attract new and retain existing businesses in Prince William County’s Innovation Park, advancing the region’s innovation industries and driving associated economic growth.

Facilities Staff Support

Planning Manno, Laura
Project Mgmt. Steele, Virginia
Hylton Performing Arts Center Addition - February 2018 - August 2019

Details

Project Number: 247-18011-000
Project Type: Performing Arts Academic Addition
Campus: Science & Technology Campus – Prince William County
Biennium: 2014 – 2016
Authorization: Authorized
Phase: Design
Key Building Occupants: CVPA – College of Visual and Performing Arts

Budget

Total Project Budget: $9,043,000
Current Budget Total: $13,481,383

Schedule

Project Authorization: July 2014
Design Start: August 2014
Design Complete: December 2017
Construction Start: February 2018
Construction Completion: August 2019
Furniture Installation Completion: August 2019
Occupancy (ready for use): 

Status

Design Nearly Complete and Construction Manager selection complete.  Projecting early 2019 project delivery.

Project Team

Owner: George Mason University
University Project Manager: Mike Herman
University Construction Manager: Mike Herman
Contractor: James G Davis Construction Corporation
Designer: Cho Benn Holback

 

Arlington Campus

  • No Current Projects

Loudoun Site

  • No Current Projects

Remote Location

  • No Current Projects

 

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

 

PROJECT ARCHIVE