Current Projects

For a list of past projects, go to the Project Archive.

Fairfax Campus

Improve Utility Distribution Infrastructure Fairfax - August 2018 - October 2021

 

Details

Project Number: 18208-000
Project Type: Construction
Campus: Fairfax
Biennium: 2016 -2018
Authorization: Authorized
Phase: Preliminary Design
Key Building Occupants:

Budget

Total Project Budget: 48,806,000
Construction Budget: 39,996,000

Schedule

Project Authorization:
Design Start: April 2016
Design Complete: August 2018
Construction Start: August 2018
Construction Completion: October 2021
Furniture Installation Completion:
Occupancy (ready for use):

Project Team

Owner: GMU
University Program Director – Cathy Pinskey
University Project Manager: Annmarie Irwin
University Construction Manager:
Construction Manager: The Whiting Turner Company
Designer: Perkins & Will

Construct/Renovate Robinson Hall and Harris Theater - September 2018 - January 2022

Details

Project Number: 18207-000
Project Type: Construction
Campus: Fairfax
Biennium: 2016 -2018
Authorization: Authorized
Phase: Preliminary Design
Key Building Occupants: CHSS, MIX, University Classrooms, ITU

Budget

Total Project Budget: 113,040,000
Construction Budget: 84,694,000

Schedule

Project Authorization
Design Start: April 2016
Design Complete: November 2018
Construction Start: September 2018
Construction Completion: January 2022
Furniture Installation Completion: December 2021
Occupancy (ready for use): January 2021 – New Robinson, January 2022 – Renovated Harris

Project Team

Owner: GMU
University Program Director: Cathy Pinskey
University Project Manager: TBD
University Construction Manager
Construction Manager: The Whiting Turner Company
Designer: Perkins & Will

 

Science and Technology Campus

Hylton Center Addition - February 2018 - December 2018

Details

Project Number: 247-18011-000
Project Type: Performing Arts Academic Addition
Campus: Science & Technology Campus – Prince William County
Biennium: 2014 – 2016
Authorization: Authorized
Phase: Design
Key Building Occupants: CVPA – College of Visual and Performing Arts

Budget

Total Project Budget: $9,043,000
Construction Budget: $7,001,000

Schedule

Project Authorization: July 2014
Design Start: August 2014
Design Complete: December 2017
Construction Start: February 2018
Construction Completion: December 2018
Furniture Installation Completion: December 2018
Occupancy (ready for use): January 2019

Status

Design Nearly Complete and Construction Manager selection complete.  Projecting early 2019 project delivery.

Project Team

Owner: George Mason University
University Project Manager: Mike Herman
University Construction Manager: Mike Herman
Contractor: Whiting Turner
Designer: Cho Benn Holback

Life Sciences - Bull Run Add DPB - TBD

Details

Project Number: 18000-000
Project Type: Construction
Campus: Prince William
Biennium: 2016 -2018
Authorization: Authorized
Phase: Planning
Key Building Occupants:

Budget

Total Project Budget: 61,500,000
Construction Budget:

Schedule

Project Authorization:
Design Start:
Design Complete:
Construction Start: August 2018
Construction Completion: September 2020
Furniture Installation Completion: September 2020
Occupancy (ready for use): September 2020

Project Team

Owner
University Project Manager: James Riddle
University Construction Manager
Contractor
Designer

 

Arlington Campus

 

Loudoun Site

 

Remote Location

 

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save