March 23, 2020

PW Life Sciences Lab Building – IABR Clean Room

10920 George Mason Circle, Manassas, VA 20109

 

Details

Project Number:  247-17848-004
Project Type:  Renovation/Improvement
Campus:  Science and Technology
Authorization:  State Legislature
Phase:  Construction
Key Building Occupants:  3rd floor

Budget

Total Project Budget:  $3,866,123

Schedule

Construction Start:  March 30, 2018
Construction Completion:  April 21, 2020

Status:  Active


Project Team

University Project Manager:  Nick Valadez

Planner:  Laura Manno

Architect/Engineer:  Cannon Washington Inc

Unit Space Liaison:   Carrie McVicker