February 20, 2020

Improve Utility Distribution Infrastructure Fairfax

Details

Project Number: 18208-000
Project Type: Renovation/Improvement
Campus: Fairfax
Biennium: 2016 -2018
Authorization: Authorized
Project Phase: Construction
Key Building Occupants:

Budget

Current Budget Total: 51,371,000

Schedule

Project Authorization:
Design Start: April 2016
Design Complete: August 2018
Construction Start: August 2018
Construction Completion: November 2021
Furniture Installation Completion:
Occupancy (ready for use):

Mason Executive Committee

Anne Holton, Interim University President
Frank Neville, Chief of Staff, Vice President, Communications and Marketing
S David Wu, Provost and Executive Vice President
Carol D. Kissal, Senior Vice President, Administration and Finance
Sean Mallon, Associate Vice President, Entrepreneurship and Innovation
Ann Ardis, Dean, College of Humanities and Social Sciences
Frank Strike, Vice President, Facilities

Mason Staffing

Cathy Wolfe-Pinskey, Program Director, Facilities
Lisa Reeves, Project Administrator
Michelle Gettle, Project Manager
Greg Rahimzadeh, Inspector
Mirwais Safi, Inspector
Fernando Acosta, Student Intern

Architect Team

Paul Harney, Architect, Principal, Perkins+Will
Sherman Lai, Project Architect, Perkins+Will
Stephanie Wolfgang, Landscape Architect, Perkins+Will
Justin Cooper, Senior Landscape Architect, Perkins+Will

Construction Manager Team

K.C. Haile, Senior Vice President, The Whiting-Turner Contracting Company
Jeff Downs, Project Manager, The Whiting-Turner Contracting Company
Perry Mahle, Project Manager, The Whiting-Turner Contracting Company
Rob Driscoll, Senior Superintendent, The Whiting-Turner Contracting Company