HVIIC- Eastern Shore Renovation

4403 Patriot Circle 
Fairfax, VA 22030

 

 PROJECT SUMMARY:
To increase bed spaces, housing would like to proceed to full design/construction to convert the current lounge spaces in Eastern Shore into student dwelling units.

 Details:
Project Number: 190768
Project Type: Renovation/Improvement
Campus: Fairfax
Authorization: Board of Visitors
Phase: Pre-design
Key Building Occupants: Housing – Auxiliary

Budget:
Total Project Budget: 4,004,000

 Schedule:
Construction Start: November 2019
Construction Completion: December 2021

Status
Active

Project Team:

University Project Manager:  Youstina Abdelmalak
Architect/Engineer:
Unit Space Liaison: Ronald C Scott