Facilities

Construct/Renovate Robinson Hall and Harris Theater

Details

Project Number: 18207-000
Project Type: New Construction
Campus: Fairfax
Authorization: Authorized
Project Phase: Construction
Key Building Occupants: CHSS, MIX, University Classrooms, ITU

Budget

Construction Budget: 108,316,000

Schedule

Project Authorization
Design Start: April 2016
Design Complete: November 2018
Construction Start: September 2018
Construction Completion: December 2021
Furniture Installation Completion: December 2021
Occupancy (ready for use): January 2022 – New Robinson, January 2022 – Renovated Harris

Mason Executive Committee

Anne Holton, Interim University President
Frank Neville, Chief of Staff, Vice President, Communications and Marketing
S David Wu, Provost and Executive Vice President
Carol D. Kissal, Senior Vice President, Administration and Finance
Sean Mallon, Associate Vice President, Entrepreneurship and Innovation
Ann Ardis, Dean, College of Humanities and Social Sciences
Frank Strike, Vice President, Facilities

Mason Staffing

Cathy Wolfe-Pinskey, Program Director, Facilities
Lisa Reeves, Project Administrator
Michelle Gettle, Project Manager
Greg Rahimzadeh, Inspector
Mirwais Safi, Inspector
Fernando Acosta, Student Intern

Architect Team

Paul Harney, Architect, Principal, Perkins+Will
Sherman Lai, Project Architect, Perkins+Will
Stephanie Wolfgang, Landscape Architect, Perkins+Will
Justin Cooper, Senior Landscape Architect, Perkins+Will

Construction Manager Team

K.C. Haile, Senior Vice President, The Whiting-Turner Contracting Company
Jeff Downs, Project Manager, The Whiting-Turner Contracting Company
Perry Mahle, Project Manager, The Whiting-Turner Contracting Company
Rob Driscoll, Senior Superintendent,