Project Listing

Projects – Archive

Fairfax Campus

Health and Human Services (AcaVII/ResIII) - June 2015 - October 2017

Details

Project Number: 17999-000
Project Type: Construction
Campus: Fairfax
Biennium: 2012 – 2014
Authorization: Authorized
Phase: Concept
Description

Provides much needed Academic & Research Space to support new CHHS
programs and program expansions
Consolidates College of Health & Human Services into one location on the
Fairfax Campus
Provides opportunities for Community Outreach and Industry Collaboration
within the included Clinic
Provides 8 new University Classrooms
Frees up space in Robinson Hall that can be used to renovate and right-size
existing University Classrooms and consolidate the College of Humanities and
Social Sciences

Key Building Occupants

College of Health & Human Services; University Classrooms; Research and Clinic
Budget

Total Project Budget $ $67,686,799
Construction Budget
Schedule

Project Authorization
Design Start: October 2012
Design Complete: September 2014
Construction Start: June 2015
Construction Completion: October 2017
Furniture Installation Completion
Occupancy (ready for use)
Status

Site construction began in July 2015.  The contractor is mobilized on site and has completed the necessary clearing work. Contractor is working on required utility and site work.  The foundation and concrete work began in October.  Scheduled opening Fall of 2017.
Project Team

Owner
University Project Manager: Alex Iszard
University Construction Manager
Contractor: Whiting Turner
Designer: Perkins Eastman

Johnson Center Dining Phase II - February 2017 - August 2017

Details

Project Number: 18172-000
Project Type: Addition
Campus: Fairfax
Biennium: 2016 -2018
Authorization: Authorized
Phase: Planning
Key Building Occupants
Budget

Total Project Budget: $4,000,000
Construction Budget
Schedule

Project Authorization
Design Start
Design Complete
Construction Start: February 2017
Construction Completion: August 2017
Furniture Installation Completion
Occupancy (ready for use)
Project Team

Owner
University Project Manager: Nancy Pickens
University Construction Manager
Contractor
Designer

Improve Utility Distribution Infrastructure Fairfax - July 2018 - March 2021

Details

Project Number: 18208-000
Project Type: Construction
Campus: Fairfax
Biennium: 2016 -2018
Authorization: Authorized
Phase: Planning
Key Building Occupants
Budget

Total Project Budget: 49,160,000
Construction Budget: 41,188,000
Schedule

Project Authorization
Design Start
Design Complete
Construction Start: July 2018
Construction Completion: March 2021
Furniture Installation Completion
Occupancy (ready for use)
Project Team

Owner: GMU
University Project Manager: Cathy Wolfe-Pinskey – Program Director
University Construction Manager
Contractor: Donley’s
Designer: Perkins & Will

Construct/Renovate Robinson Hall and Harris Theater - April 2018 - May 2022

Details

Project Number: 18207-000
Project Type: Construction
Campus: Fairfax
Biennium: 2016 -2018
Authorization: Authorized
Phase: Planning
Key Building Occupants
Budget

Total Project Budget: 111,790,000
Construction Budget: 82,104,000
Schedule

Project Authorization
Design Start
Design Complete
Construction Start: April 2018
Construction Completion: May 2022
Furniture Installation Completion
Occupancy (ready for use)
Project Team

Owner: GMU
University Project Manager: Cathy Wolfe-Pinskey – Program Director
University Construction Manager
Contractor: Donley’s
Designer: Perkins & Will

Science and Tech Campus

Hylton Center Addition - April 2017 - April 2018

Hylton Center Addition

Hylton Center Addition

Details

Project Number: 18011-000
Project Type: Addition
Campus: Prince William
Biennium: 2014 – 2016
Authorization: Authorized
Phase: Design
Key Building Occupants
Budget

Total Project Budget: $9,043,000
Construction Budget
Schedule

Project Authorization
Design Start
Design Complete
Construction Start: April 2017
Construction Completion: April 2018
Furniture Installation Completion
Occupancy (ready for use)
Status

Design contract awarded and Construction Manager selection complete.  Projecting Fall 2016 project delivery.
Project Team

Owner
University Project Manager: Mike Herman
University Construction Manager
Contractor
Designer

PPEA Discovery Hall Ph II & Fitout - May 2017 - February 2018

Details

Project Number: 17848-000
Project Type: Construction
Campus: Prince William
Biennium: 2014 – 2016
Authorization: Authorized
Phase: Design
Description

-In order to maximize the effectiveness and efficiency of executing the PPEA Discovery Hall Phase II & Fit-out project, we developed a sole source justification to use the same Architect and Engineering firm and subsequently negotiated the appropriate fee amount.Following this prolonged process, the project execution schedule was adjusted with a completion date of March 2017.  Details of the new schedule are shown below:

1) Design/Review/Permits – 35 weeks

2) Construction Contract Bid & Award – 8 weeks

3) Construction – 22 weeks

4) Equipment/Commissioning/Punch list/Training – 8 weeks
Key Building Occupants
Budget

Total Project Budget: $3,800,000
Construction Budget
Schedule

Project Authorization
Design Start
Design Complete
Construction Start: May 2017
Construction Completion: February 2018
Furniture Installation Completion
Occupancy (ready for use)
Status

The project execution schedule was adjusted with a completion date of March 2017.
Project Team

Owner
University Project Manager
University Construction Manager
Contractor
Designer

Life Sciences - Bull Run Add DPB - TBD

Details

Project Number: 18000-000
Project Type: Construction
Campus: Prince William
Biennium: 2016 -2018
Authorization: Authorized
Phase: Planning
Key Building Occupants
Budget

Total Project Budget: 61,500,000
Construction Budget
Schedule

Project Authorization
Design Start
Design Complete
Construction Start: August 2018
Construction Completion: September 2020
Furniture Installation Completion: September 2020
Occupancy (ready for use): September 2020
Project Team

Owner
University Project Manager: James Riddle
University Construction Manager
Contractor
Designer

Arlington Campus

Hazel Hall Library Renovation - 1st and 2nd Floors - August 2017 - December 2017

Details

Project Number: 18252-000
Project Type: Renovation
Campus: Arlington
Biennium: 2016 -2018
Authorization: Authorized
Phase: Design
Key Building Occupants
Budget

Total Project Budget: $2,600,000
Construction Budget
Schedule

Project Authorization
Design Start
Design Complete
Construction Start: August 2017
Construction Completion: December 2017
Furniture Installation Completion: December 2017
Occupancy (ready for use) December 2017
Project Team

Owner
University Project Manager
University Construction Manager
Contractor
Designer

Loudoun Campus

Remote Location

Potomac Science Center - October 2014 - March 2017

Details

Project Number: 17634-000
Project Type: Construction
Campus: Remote Location
Biennium: 2012 – 2014
Authorization: Authorized
Phase: Construction
Description

• Provides much needed Environmental Science Research Space along the Chesapeake Bay Watershed

• Provides enhanced opportunities for GIS collaboration with government agencies and private industry

• Supports educational outreach to local public schools
Key Building Occupants

COS, Community Outreach
Budget

Total Project Budget: $32,579,166
Construction Budget
Schedule

Project Authorization
Design Start: October 2012
Design Complete: June 2014
Construction Start: October 2014
Construction Completion: March 2017
Furniture Installation Completion: March 2017
Occupancy (ready for use) March 2017
Status

Construction is ongoing. The science center superstructure is nearing completion. Interior work including framing, structural steel, plumbing, HVAC and electrical work is ongoing. The parking garage structure is complete. Occupancy scheduled for June 2016.
Project Team

Owner
University Project Manager: James Riddle
University Construction Manager Developer: Belmont Mason LLC
Contractor: EE Reed
Designer: Zimmer Gunsul Frasca Architects and HKS

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save

Save