Project Listing

Projects – Archive

Fairfax Campus

Health and Human Services (AcaVII/ResIII) - June 2015 - December 2017

Details

Project Number: 17999-000
Project Type: Construction
Campus: Fairfax
Biennium: 2012 – 2014
Authorization: Authorized
Phase: Construction

Description

Provides much needed Academic & Research Space to support new CHHS
programs and program expansions
Consolidates College of Health & Human Services into one location on the
Fairfax Campus
Provides opportunities for Community Outreach and Industry Collaboration
within the included Clinic
Provides 8 new University Classrooms
Frees up space in Robinson Hall that can be used to renovate and right-size
existing University Classrooms and consolidate the College of Humanities and
Social Sciences

Key Building Occupants

College of Health & Human Services; University Classrooms; Research and Clinic

Budget

Total Project Budget: $ $71,198,234
Construction Budget: $54,851,558

Schedule

Project Authorization:
Design Start: October 2012
Design Complete: September 2014
Construction Start: June 2015
Construction Completion: December 2017
Furniture Installation Completion: December 2017
Occupancy (ready for use): December 2017

Status

Site construction began in July 2015.   The building is progressing towards substantial completion. Within the building, interior work is being completed by the contractor at the same time that AV and furniture install are being completed. Outside of the building, final sitework and landscaping are ongoing.  Scheduled opening late Fall of 2017.

 

Project Team

Owner:
University Project Manager: Alex Iszard
University Construction Manager
Contractor: Whiting Turner
Designer: Perkins Eastman

Improve Utility Distribution Infrastructure Fairfax - August 2018 - October 2021

 

Details

Project Number: 18208-000
Project Type: Construction
Campus: Fairfax
Biennium: 2016 -2018
Authorization: Authorized
Phase: Preliminary Design
Key Building Occupants:

Budget

Total Project Budget: 48,806,000
Construction Budget: 39,996,000

Schedule

Project Authorization:
Design Start: April 2016
Design Complete: August 2018
Construction Start: August 2018
Construction Completion: October 2021
Furniture Installation Completion:
Occupancy (ready for use):

Project Team

Owner: GMU
University Project Manager: Cathy Wolfe-Pinskey – Program Director
University Construction Manager
Contractor: Donley’s
Designer: Perkins & Will

Construct/Renovate Robinson Hall and Harris Theater - September 2018 - January 2022

Details

Project Number: 18207-000
Project Type: Construction
Campus: Fairfax
Biennium: 2016 -2018
Authorization: Authorized
Phase: Preliminary Design
Key Building Occupants: CHSS, MIX, University Classrooms, ITU

Budget

Total Project Budget: 113,040,000
Construction Budget: 84,694,000

Schedule

Project Authorization
Design Start: April 2016
Design Complete: November 2018
Construction Start: September 2018
Construction Completion: January 2022
Furniture Installation Completion: December 2021
Occupancy (ready for use): January 2021 – New Robinson, January 2022 – Renovated Harris

Project Team

Owner: GMU
University Project Manager: Cathy Wolfe-Pinskey – Program Director
University Construction Manager
Contractor: Donley’s
Designer: Perkins & Will

Science and Tech Campus

Hylton Center Addition - February 2018 - December 2018

Details

Project Number: 247-18011-000
Project Type: Performing Arts Academic Addition
Campus: Science & Technology Campus – Prince William County
Biennium: 2014 – 2016
Authorization: Authorized
Phase: Design
Key Building Occupants: CVPA – College of Visual and Performing Arts

Budget

Total Project Budget: $9,043,000
Construction Budget: $7,001,000

Schedule

Project Authorization: July 2014
Design Start: August 2014
Design Complete: December 2017
Construction Start: February 2018
Construction Completion: December 2018
Furniture Installation Completion: December 2018
Occupancy (ready for use): January 2019

Status

Design Nearly Complete and Construction Manager selection complete.  Projecting early 2019 project delivery.

Project Team

Owner: George Mason University
University Project Manager: Mike Herman
University Construction Manager: Mike Herman
Contractor: Whiting Turner
Designer: Cho Benn Holback

PPEA Discovery Hall Ph II & Fitout - May 2017 - February 2018

Details

Project Number: 17848-000
Project Type: Construction
Campus: Prince William
Biennium: 2014 – 2016
Authorization: Authorized
Phase: Design

Description

-In order to maximize the effectiveness and efficiency of executing the PPEA Discovery Hall Phase II & Fit-out project, we developed a sole source justification to use the same Architect and Engineering firm and subsequently negotiated the appropriate fee amount.Following this prolonged process, the project execution schedule was adjusted with a completion date of March 2017.  Details of the new schedule are shown below:

1) Design/Review/Permits – 35 weeks

2) Construction Contract Bid & Award – 8 weeks

3) Construction – 22 weeks

4) Equipment/Commissioning/Punch list/Training – 8 weeks

Key Building Occupants

Budget

Total Project Budget: $3,800,000
Construction Budget:

Schedule

Project Authorization:
Design Start:
Design Complete:
Construction Start: May 2017
Construction Completion: February 2018
Furniture Installation Completion:
Occupancy (ready for use):

Status

The project execution schedule was adjusted with a completion date of March 2017.

Project Team

Owner:
University Project Manager:
University Construction Manager:
Contractor:
Designer

Life Sciences - Bull Run Add DPB - TBD

Details

Project Number: 18000-000
Project Type: Construction
Campus: Prince William
Biennium: 2016 -2018
Authorization: Authorized
Phase: Planning
Key Building Occupants:

Budget

Total Project Budget: 61,500,000
Construction Budget:

Schedule

Project Authorization:
Design Start:
Design Complete:
Construction Start: August 2018
Construction Completion: September 2020
Furniture Installation Completion: September 2020
Occupancy (ready for use): September 2020

Project Team

Owner
University Project Manager: James Riddle
University Construction Manager
Contractor
Designer

Arlington Campus

Hazel Hall Library Renovation - 1st and 2nd Floors - August 2017 - November 2017


Details

Project Number: 18252-000
Project Type: Renovation
Campus: Arlington
Biennium: 2016 -2018
Authorization: Authorized
Phase: Design
Key Building Occupants:

Budget

Total Project Budget: $2,600,000
Construction Budget

Schedule

Project Authorization
Design Start
Design Complete
Construction Start: August 2017
Construction Completion: November 2017
Furniture Installation Completion: November 2017
Occupancy (ready for use): November 2017

Project Team

Owner:
University Project Manager:  Thomas Olund
Contractor:
Designer: