Details  ::  Description  ::  Departments Involved  ::  Budget  ::  Schedule  ::  Status  ::  Project Stakeholders  

 
 
 

Updated as of 07/10/2008

 


 
Project Number 247-17142
Project Type Construction
Campus Fairfax
Biennium 2004 - 2006
Authorization Authorized
Phase Design


 

This project constructs a 50,000 SF building for use as Fairfax campus swing space. 25,000 SF will be devoted as space required for relocating units from other buildings scheduled for renovation. The other 25,000 SF will be constructed as permanent location for the University Data Center. The project schedule is connected to renovation schedules of Thompson and West Halls. Work cannot begin on the Swing Space building until after completion of West Hall.

Design- Build Project

 


 
Provost, ITU


 
Total Project Budget $8,700,000
Construction Budget $7,100,000


 
 
 

PLANNED

CURRENT
Project Authorization Jul 04 Jul 04
Design Start Dec 05 Feb 07
Design Complete Mar 06 May 08
Construction Start: Jul 06 Feb 08
Construction Completion: Jul 07 Feb 10
Furniture Installation Completion: Jul 07 Feb 10
Occupancy  (Ready for Use): Jul 07 Feb 10
 


 

The Request for Proposals has been received from the short listed firms for the Fairfax Swing Space/Data Center.  The proposals are being evaluated and technical presentations were held on November 14.  With completion of this swing space, we will relocate Thompson Hall occupants and begin, in two phases, whole building renovation in Thompson. 

     


 
Owner  
University Project Manager
 
Mike Herman
University Construction Manager  
Contractor  
Designer Burt, Hill, Kosar, Rittelmann and Associates
 