 Upgrade Master Plan
 

 

4400 University Drive, MS 1E4
Fairfax, Virginia  22030

[ Map / Directions ]


INFO:
8 am - 5 pm

After hours

FAX:



703-993-2520
703-993-2525

703-993-2524

 

 
 

Details  ::  Description  ::  Departments Involved  ::  Budget  ::  Schedule  ::  Status  ::  Project Stakeholders  

 
 
 

2/01/2006

 


 
Project Number NC-05-002
Project Type Renovation
Campus Fairfax
Biennium 2004 - 2006
Authorization Authorized
Phase Construction


  Project converts grass field to artificial surface and renovates the existing field lighting system.  


 


 
Total Project Budget $1,000,000
Construction Budget $900,000


 
 
 

PLANNED

CURRENT
Project Authorization   May 05
Design Start   May 05
Design Complete Aug 05 Aug 05
Construction Start:   Sep 05
Construction Completion: Oct 05 Oct 05
Furniture Installation Completion:   Dec 05
Occupancy  (Ready for Use): Apr 06
 


 

 
  • Field installation complete
  • Final dressing of area outside field to be complete 1st week of February
  • Awaiting Dominion to energize lights. Siemens making final electrical connections to be ready for Dominion
  • Lights energized. Two bad bulbs to be re-placed
  • Musco to conduct field tests in late April/early May
 


 
Owner  
University Project Manager
 
Tom Calhoun
University Construction Manager  
Contractor  
Designer  
 

Please direct all project-related inquiries to the University Project Manager.

Webmaster   |   Copyright © 2005 Facilities Division. All rights reserved.  |   Page Last Updated: 04.19.2006 12:16 PM