 Performing Arts Addition

 

Details  ::  Description  ::  Departments Involved  ::  Budget  ::  Schedule  ::  Status  ::  Project Stakeholders  

 
 
 

 

 


 
Project Number 247-17097
Project Type Construction
Campus Fairfax
Biennium 2006 - 2008
Authorization Authorized
Phase Design


  The addition to the Perfroming Arts Building, to be used by the College of Visual and Performing Arts, will include teaching and practice areas for large instruments ensembles and dance programs. An entry area commensurate with the theater nature and scale of this building will provide a new entrance into the building.  


 
CVPA


 
Total Project Budget $10,000,000
Construction Budget $ 5,860,000


 
 
 

PLANNED

CURRENT
Project Authorization July 2006 July 2006
Design Start Aug 2006 Aug 2007
Design Complete Apr 2007 Feb 2009
Construction Start: Oct 2007 Jun 2009
Construction Completion: Dec 2008 Jul 2010
Furniture Installation Completion:   Jul 2010
Occupancy  (Ready for Use):   Jul 2010
 


 

This project will add dance and orchestra practice and performance spaces and a wellness center to the Performing Arts Building at Fairfax.  It will be funded by a combination of General Funds and private donations. 

     


 
Owner Brian Marcus

 Project Manager

Nancy S. Pickens

 

University Construction Manager

 

Bob Endebrock

 

Contractor

 


 

Designer

 

Hughes Group Architects

 

Please direct all project-related inquiries to the University Project Manager.

Webmaster   |   Copyright © 2005 Facilities Division. All rights reserved.  |