Project Number |
247-17054 |
|
Project Type |
Addition & Renovation |
|
Campus |
Fairfax |
|
Biennium |
2006 -
2008 |
|
Authorization |
Authorized |
|
Phase |
Design |
|
|
|
|
| |

|
|
|
|
|
| |
Renovations of existing areas such as exercise room, classroom, locker rooms, toilet rooms, training facilities, storage area, electrical distribution areas, and circulation. Expansion areas include primary building circulation with lobby and juice bar, new gym for recreation and competitive use, squash & racquetball courts, fitness & training center, multi-purpose room, and office area. Scope includes new MEP/FP systems and central plant as well as upgrades to existing Linn and Cage Gyms. At least one gym will remain open. |
|
|
|
| |
 |
| |
Athletics, ICA, ROTC |
 |
| |
|
|
|
|
| Total
Project Budget |
$28,859,000 |
|
Construction Budget |
$24,121,000 |
|
|
|
|
| |
 |
| |
|
|
|
| |
| |
PLANNED |
CURRENT |
| Project Authorization |
|
July 04 |
| Design
Start |
|
Sep 05 |
| Design
Complete |
Sep 06 |
Sep 07 |
| Construction Start: |
Oct 06 |
Oct 07 |
| Construction Completion: |
Aug 08 |
Apr 09 |
| Furniture
Installation Completion: |
Aug 08 |
Apr 09 |
|
|
|
| Occupancy
(Ready for Use): |
Aug 08 |
May 09 |
|
|
|
|
| |
 |
| |
|
This multi-phase project adds courts and fitness areas to the existing Physical Education building. This project also adds a new Wrestling and Volleyball venue to the building. Ewing Cole of Washington, DC and Philadelphia.
|
|
| |
|
|
|
|
| |
|
 |
|
Please direct all project-related