Updated as of 07/10/2008

 


 
Project Number 247-16690
Project Type Renovation
Campus Fairfax
Biennium 2002 - 2004
Authorization Authorized
Phase Design


  Interior renovations and masonry cleaning of Commonwealth and Dominion complete Reroofing project at both buildings to be completed during summer '08 to eliminate unstable parapet and leaking roofs.  


 
Student Services


 
Total Project Budget $1,772,000
Construction Budget $1,500,000


 
 
 

PLANNED

CURRENT
Project Authorization Aug 02 Aug 02
Design Start Sep 02 Sep 05
Design Complete Feb 03 Feb 08
Construction Start: May 03 May 08
Construction Completion: Aug 06 Aug 08
Furniture Installation Completion: Aug 03 Aug 08
Occupancy  (Ready for Use): Aug 03 Aug 08
 


 

Gauthier Alvarado and Associates has completed preliminary design for the exterior upgrades to the facades and roof replacement for Dominion and Commonwealth Halls to be completed in Summer 2008.   

     


 
Owner John Spaldo
University Project Manager
 
Nancy Pickens
University Construction Manager Bob Endebrock
Contractor  
Designer Gauthier Alvarado and Associates
 

Please direct all project-related inquiries to the University Project Manager.