Sc &Tech 2 (Ren & Add)

 

Details  ::  Description  ::  Departments Involved  ::  Budget  ::  Schedule  ::  Status  ::  Project Stakeholders  

 
 
 

 


 
Project Number 247-17698
Project Type Addition & Renovation
Campus Fairfax
Biennium 2008-2010
Authorization Authorized
Phase Construction


 

This will be a complete renovation of the building and re-assign space to departments. It will include a combination of biology, geology and ESP teaching labs in the 50,000 GSF addition to the building which will connect Science and Tech I and II. 20 teaching labs will be provided within the building addition. Total renovated gross square footage of this building is 100,000. The total addition to the building is 50,000 GSF and will include infrastructure and loading dock upgrades.

•Completes the consolidation of the College of Science into one area of campus (David King Hall, Science and Technology I and II, Research Hall) as outlined in the University’s College Co-Location Master Plan

•Provides modern science teaching labs to meet STEM instructional needs and support science education across the University

•Provides University classrooms that include updated technology standards to meet faculty pedagogical needs

 

 


 
COS


 
Total Project Budget $52,198,285
Construction Budget $40,000,000


 
 
 

PLANNED

CURRENT
Project Authorization Jul 2008 Jul 2008
Design Start Oct 2008 Feb 2009
Design Complete Apr 2010 Apr 2010
Construction Start: Jan 2010 Jan 2011
Construction Completion: Jan 2012 May 2013
Furniture Installation Completion: Jul 2012 May 2013
Occupancy  (Ready for Use): Aug 2012 May 2013
 


 

 

     


 
Owner Vikas Chandhoke
University Project Manager
 
 
University Construction Manager Alex Iszard
Contractor Donley's LLC
Designer Perkins and Will
 

Please direct all project-related inquiries to the University Project Manager.