Project is to create a masterplan for the site on Belmont Bay to include living, teaching, reasearch and conference spaces.
ICAR
Total
Project Budget
$10,000,000
Construction Budget
$
PLANNED
CURRENT
Project Authorization
Jul 04
Jul 04
Design
Start
Aug 06
Aug 06
Design
Complete
Dec 07
Construction Start:
Jan 09
Construction Completion:
Dec 10
Furniture
Installation Completion:
Dec 10
Occupancy
(Ready for Use):
Dec 10
The architectural firm of Bushman Dreyfus has been meeting with ICAR, the University community and surrounding neighbors to promote discussions and ideas for the master plans for Point of View Conference Center. The master plan will provide a definitive direction for the project and will assist ICAR with fundraising efforts. We will proceed further with design and construction after successful fundraising.