Project Number 247-17697
Project Type Renovation
Campus Fairfax
Biennium 2008-2010
Authorization Authorized
Phase Design


 

This project will require the addition of acoustical treatments and separations, addition of special floor and wall treatments to support performance space requirements as well as typical interior partition modifications. It will include mechanical and infrastructure upgrades, complete roof replacement, an enclosed connection to the PAB and a loading dock and convenience doors for the art studios.

 


 
 


 
Total Project Budget $9,807,000
Construction Budget  


 
 
 

PLANNED

CURRENT
Project Authorization Jul 2008 Jul 2008
Design Start Apr 2009 Apr 2009
Design Complete Feb 2011 Feb 2011
Construction Start: Mar 2011 Mar 2011
Construction Completion: May 2012 May 2012
Furniture Installation Completion: May 2012 May 2012
Occupancy  (Ready for Use): May 2012 May 2012
 


 

 

     


 
Owner Bill Reeder
University Project Manager
 
Eric Backus
University Construction Manager  
Contractor  
Designer Ayers Saint Gross
   
 