Details  ::  Description  ::  Departments Involved  ::  Budget  ::  Schedule  ::  Status  ::  Project Stakeholders  

 
 
 

 

 

 
Project Number 247-17143-002
Project Type Construction
Campus Fairfax
Biennium 2006 - 2008
Authorization Authorized
Phase Planning


  This project expands upon the Field house by increasing the training facilities, strenght and conditioning areas, and resurfacing of the infield of the building.  


 
Athletics


 
Total Project Budget $4,815,000
Construction Budget $4,815,000


 
 
 

PLANNED

CURRENT
Project Authorization Jul 2006 Jul 2006
Design Start Oct 2008 Mar 2009
Design Complete    
Construction Start:    
Construction Completion:    
Furniture Installation Completion:    
Occupancy  (Ready for Use):    
 


 

     


 
Owner Mickey Mc Dade
University Project Manager
 
Erik Backus
University Construction Manager Bob Endebrock
Contractor
Designer Gauthier, Alvarado & Associates/HNTB
 

Please direct all project-related inquiries to the University Project Manager.