Fenwick Library Addition
|
| |
Details
:: Description ::
Departments Involved ::
Budget ::
Schedule ::
Status ::
Project Stakeholders |
| |
 |
|
| |
 |
| |
|
|
|
|
|
Project Number |
247-17695 |
|
Project Type |
Addition |
|
Campus |
Fairfax |
|
Biennium |
|
|
Authorization |
Authorized |
|
Phase |
Design |
|
|
|
|
| |

|
|
|
|
|
| |
The construction of a 150,000 GSF addition to Fenwick Library will reposition George Mason University's largest library as the main research library and as the "network hub" for the Johnson Center. The campus master plan calls for demolition of both the existing library's wing A and the connector space between this wing (35,000 GSF) and the two towers ( Wings B & C )
|
|
|
|
| |
 |
| |
|
 |
| |
|
|
|
|
| Total
Project Budget |
$57,000,000 |
|
Construction Budget |
$43,500,000 |
|
|
|
|
| |
 |
| |
|
|
|
| |
| |
PLANNED |
CURRENT |
| Project Authorization |
Jul 2008 |
Jul 2008 |
| Design
Start |
Aprl 2009 |
Aprl 2009 |
| Design
Complete |
Dec 2010 |
Dec 2010 |
| Construction Start: |
Jan 2011 |
Jan 2011 |
| Construction Completion: |
Dec 2012 |
Dec 2012 |
| Furniture
Installation Completion: |
Jan 2012 |
Jan 2012 |
|
|
|
| Occupancy
(Ready for Use): |
Feb 2012 |
Feb 2012 |
|
|
|
|
| |
 |
| |
|
Preliminary design in progress, architect under contract and performing user interviews and developing building program.
|
|
| |
|
|
|
|
| |
|
 |
|