•The construction of this addition will reposition Mason’s largest library as the main research library for the University and as a “network” hub for the Johnson Center.
•This project will re-purpose the existing Fenwick Library to meet the demands of Mason’s growing, increasingly residential undergraduate student population; a strong focus on graduate education and research; and a higher caliber of undergraduate and graduate students.
University Community
Total
Project Budget
$57,369,000
Construction Budget
PLANNED
CURRENT
Project Authorization
Jul 2008
Jul 2008
Design
Start
Aprl 2009
Aprl 2009
Design
Complete
Dec 2010
Dec 2011
Construction Start:
Jan 2011
Nov 2012
Construction Completion:
Dec 2012
May 2015
Furniture
Installation Completion:
Jan 2012
May 2015
Occupancy
(Ready for Use):
Jan 2013
May 2015
Preliminary design in progress, architect under contract and performing user interviews and developing building program.