FXDiningEnhancements  
 

Details  ::  Description  ::  Departments Involved  ::  Budget  ::  Schedule  ::  Status  ::  Project Stakeholders  

 
 
 

 


 
Project Number 17917-000
Project Type Construction
Campus Fairfax
Biennium 2010-2012
Authorization Authorized
Phase Construction


 

 

 

 

 


 
 


 
Total Project Budget


$17,000,000

 
Construction Budget  


 
 
 

PLANNED

CURRENT
Project Authorization    
Design Start    
Design Complete    
Construction Start:   August 2013
Construction Completion:    
Furniture Installation Completion:    
Occupancy  (Ready for Use):   August 2014
 


 

 

     


 
Owner  
University Project Manager
 
 
University Construction Manager  
Contractor TBD
Designer WBA & Gensler
   
 

Please direct all project-related inquiries to the University Project Manager.