Health and Human Services (AcaVII/ResIII)

Details

Project Number 17999-000
Project Type Construction
Campus Fairfax
Biennium 2012 – 2014
Authorization Authorized
Phase Concept

Description

  • Provides much needed Academic & Research Space to support new CHHS
    programs and program expansions
  • Consolidates College of Health & Human Services into one location on the
    Fairfax Campus
  • Provides opportunities for Community Outreach and Industry Collaboration
    within the included Clinic
  • Provides¬†8 new University Classrooms
  • Frees up space in Robinson Hall that can be used to renovate and right-size
    existing University Classrooms and consolidate the College of Humanities and
    Social Sciences

 

Key Building Occupants

College of Health & Human Services; University Classrooms; Research and Clinic

Budget

Total Project Budget $ $67,686,799
Construction Budget

Schedule

Project Authorization
Design Start October 2012
Design Complete September 2014
Construction Start June 2015
Construction Completion October 2017
Furniture Installation Completion
Occupancy (ready for use)

Status

Site construction began in July 2015. The contractor is mobilized on site and has completed the necessary clearing work. Contractor is working on required utility and site work. The foundation and concrete work began in October. Scheduled opening Fall of 2017.

Project Team

Owner
University Project Manager Alex Iszard
University Construction Manager
Contractor Whiting Turner
Designer Perkins Eastman